Kuantan Community Hall Roof
Thirteen 30 m steel trusses for a community hall roof, fabricated in Shah Alam, trucked across the Titiwangsa range and lifted in four days.
- Sector
- Institutional
- Location
- Kuantan, Pahang
- Year
- 2019
- Steel
- 85 tonnes
- Scope
- Steel roof trusses for a 30 m hall
- Client
- Main contractor, community hall
- Duration
- 8 weeks
- Services
- Structural steelwork
Overview
Each truss was fabricated in two halves to fit on a standard trailer and bolted together at ground level on site, then lifted onto the hall walls by a 50-tonne crane.
With a coastal site in mind, the trusses were blasted and coated with a three-coat system rated for a marine environment.
Finishes specified
Structural steel S355
Epoxy and polyurethane
Gallery
-
Trusses being lifted onto the hall walls -
The hall from the opposite side -
Truss halves waiting on site