Industrial
Kulim Factory Extension
Four new bays added to a working factory, with 10-tonne overhead crane beams and a 400 m² office mezzanine, tied in without stopping production.
- Sector
- Industrial
- Location
- Kulim, Kedah
- Year
- 2023
- Steel
- 680 tonnes
- Scope
- Portal frame extension with crane beams
- Client
- Precision equipment maker
- Duration
- 24 weeks
- Services
- Structural steelwork, Mezzanine floors
Overview
The new frame had to meet the old one without a single day of shutdown. We surveyed the existing gable, opened it one bay at a time behind temporary sheeting, and tied the new rafters in over three weekends.
Crane beams were set to a tight tolerance so the client's new overhead cranes ran true from the first test lift.
Finishes specified
Structural steel S355
Epoxy and polyurethane
Gallery
-
Crane beams and rafters in the new bays -
The extension from the opposite side -
New frame against the existing factory